Qwuloolt Estuary Restoration Project of the Tulalip Tribes - Shoreline Restoration

Restoration Plan

Timeline

TASKDATE

Preliminary Designs

Community Meeting & Public Comment

Final Designs

Construction of Setback Levee

Tidal Restoration (Levee and Tide Gate Removal)

January 2008

February - May 2009

May - June 2012

June 2013 - June 2015

August 2015